First Steel Structure Hoisting for Main Plant Building of Mymensingh Project in Bangladesh Successfully Completed
Recently, Harbin Electric International Co., Ltd. successfully completed the first steel structure hoisting for the main plant building of the Mymensingh 420MW Combined-cycle Project in Bangladesh. Th...… - 17 04 / 2024
First Main Transformer for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan Successfully Shipped
On April 15, the body of the first main transformer for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan, undertaken by Harbin Electric International Co., Ltd., was successfully...… - 06 04 / 2024
First Gas Turbine and Gas Turbine Generator for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan Successfully Shipped
On April 5, the load-out and shipment package including first gas turbine, gas turbine generator, and other core equipment for the Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekist...…
-
Hualong One Unit K3 of Karachi Nuclear Power Plant Passes Provisional Acceptance
On April 18th, local time, Unit K3 of the Karachi Nuclear Power Plant in Pakistan, which uses China's third-generation Hualong One nuclear reactor, the fourth unit in the world and second overseas, passed its provisional acceptance, marking the first four Hualong One reactors with the main pumps supplied by Harbin Electric Power Equipment Company Limited: Karachi Units K2 and K3 have now been fully completed and put into operation, following Fuqi...…1309 -
Steam Blowing of HRSG #1 and Hydrostatic Test of HRSG #2 of BQPS-III Project Successfully Completed
On March 29th, local time, the steam blowing of HRSG #1 and the hydrostatic test of HRSG #2 of HEI’s Pakistan BQPS-III Project were successfully completed.1198 -
Steam Blowing Successfully Completed for Unit #3 of Dubai Hassyan Project
At 13:25 on March 26th, local time, the key milestone of boiler steam blowing for Unit #3 of HEI’s Dubai Hassyan Project was successfully completed, laying a solid foundation for the unit’s first connection to the grid.1181 -
First Successful Ignition of Gas Turbine #1 of Pakistan 900 MW Combined Cycle BQPS-III Project
At 13:30 on March 14th, local time, gas turbine #1 of HEI’s Pakistan 900 MW Combined Cycle BQPS-III Project was successfully ignited for the first time with normal and stable parameters across the board1227 -
Successful Completion of 72-hour Reliability Operation Test at Iraq Basra Project
At 17:38 on February 7th (Iraq local time), the 72-hour reliability operation test of Unit #1 of the Basra Project in Iraq, the equipment of which was supplied by Harbin Turbine Company Limited, was successfully completed with excellent performance indicators, marking a good start to the new year!1281