Steam Blowing Successfully Completed for Unit #3 of Dubai Hassyan Project

Date:2022-03-28 1182Font scaling:
 

01_编辑.jpg

At 13:25 on March 26th, local time, the key milestone of boiler steam blowing for Unit #3 of HEI’s Dubai Hassyan Project was successfully completed, laying a solid foundation for the unit’s first connection to the grid.

In order to successfully complete the boiler steam blowing work of Unit #3, the project department actively coordinated with the owner and other relevant parties, undertook careful planning and close cooperation, learned from the successful experience of the previous two units, and made every effort to secure the progress of the steam blowing while ensuring its quality.