First Steel Structure Hoisting for Main Plant Building of Mymensingh Project in Bangladesh Successfully Completed
Recently, Harbin Electric International Co., Ltd. successfully completed the first steel structure hoisting for the main plant building of the Mymensingh 420MW Combined-cycle Project in Bangladesh. Th...… - 17 04 / 2024
First Main Transformer for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan Successfully Shipped
On April 15, the body of the first main transformer for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan, undertaken by Harbin Electric International Co., Ltd., was successfully...… - 06 04 / 2024
First Gas Turbine and Gas Turbine Generator for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan Successfully Shipped
On April 5, the load-out and shipment package including first gas turbine, gas turbine generator, and other core equipment for the Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekist...…
-
Two-stage Coal Unloading Performance Test of the Dubai Hassyan Project’s Coal Handling System Successfully Completed
At 4:34 am on July 20, Dubai local time, the two-stage coal unloading performance test of the coal handling system of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project contracted by HEI was successfully completed, unloading a total of 250,000 tons of coal.1651 -
Dubai Hassyan Project Unit #1’s Successful Dual-fuel Full-load Power Generation
At 19:28 on July 19, Dubai local time, Unit #1 of the Dubai Hassyan 4x600MW Clean Coal-fired Power Plant Project contracted by HEI successfully generated coal-fired full-load power, with normal parameters, stable equipment operation and excellent operation performance.1636 -
First Cubic Meter of Concrete Successfully Poured for the Foundation Pile Cap of the BQPS-III HRSG in Pakistan
At 16:38 on July 15, Pakistan local time, the HRSG #1 foundation pile cap of the 900MW Bin Qasim Combined-cycle Power Station III (BQPS-III) contracted by HEI saw its first cubic meter of concrete poured.1527 -
First-Time Successful Completion of the Dubai Hassyan Project Unit #2’s Boiler Hydrostatic Test
At 17:35 on July 3, Dubai local time, the Unit #2 boiler hydrostatic test of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project contracted by HEI was completed successfully, which marked the substantial completion of the installation of Unit #2’s main boiler components, creating favorable conditions for subsequent boiler thermal insulation and laying a solid foundation for Unit #2 boiler acid pickling and ignition venting.1472 -