First Steel Structure Hoisting for Main Plant Building of Mymensingh Project in Bangladesh Successfully Completed
Recently, Harbin Electric International Co., Ltd. successfully completed the first steel structure hoisting for the main plant building of the Mymensingh 420MW Combined-cycle Project in Bangladesh. Th...… - 17 04 / 2024
First Main Transformer for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan Successfully Shipped
On April 15, the body of the first main transformer for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan, undertaken by Harbin Electric International Co., Ltd., was successfully...… - 06 04 / 2024
First Gas Turbine and Gas Turbine Generator for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan Successfully Shipped
On April 5, the load-out and shipment package including first gas turbine, gas turbine generator, and other core equipment for the Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekist...…
-
Dubai Hassyan Project Unit #1 Island Test Successfully Completed
At 16:43 on November the 18th, Dubai local time, Unit #1 of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project, the first clean coal-fired power plant in the Middle East and a major international cooperation project under the Belt and Road Initiative contracted by HE, successfully passed its island test and was reconnected to the grid.1840 -
Showing the Style of HE through Joint Construction of “The Belt and Road” – Hai Duong BOT Thermal Power Plant Unit #1 Successfully Passed 336h Trial Operation
At 18:00 on November the 17th, Beijing Time, the Hai Duong BOT Thermal Power Plant Unit #1 with steam turbine generator units provided by HE successfully passed its 336h trial operation. During the trial operation, the unit operated in a stable manner, with various parameters and performance indicators meeting or functioning better than its design values.1803 -
The Belt and Road | GIS Room Roofs of Offsite KTPS and Landhi Substations of BQPS-III Successfully Poured
On November the 2nd and 3rd, the GIS room roofs of the offsite KTPS and Landhi substations of the 900MW Combined-cycle BQPS-III contracted by HEI were poured respectively, with a total of 193 m3 concrete, which marks the completion of the construction of the main structure of the GIS room, laying a solid foundation for subsequent masonry works.1828 -
One Belt One Road | Hardworking Gift for National Day The Foundation Concrete Pouring of the Unit 4 Heat Recovery Steam Generator of Amara project in Iraq is Successfully Completed
At 9 o'clock on October 6th, local time, the concrete pouring work for the foundation of the Unit 4 heat recovery steam generator of Iraq Amara project undertaken by HEI was successfully completed, which took 13 hours.2018 -
One Belt One Road | National Day Gifts First Concrete Pouring of Unit 4 Foundation of Dubai Hassyan Clean Coal-fired Power Plant Project is Successfully Completed
At 19:00 on October 2nd, local time, the first concrete pouring of Unit 4 foundation of Dubai Hassyan 4×600MW clean coal-fired power station project undertaken by HEI was successfully completed.1781