Lifting and Installation of Pakistan Jamshoro Project Unit #1 Generator Stator Successfully Completed
At 12:58PM on February 28, local time, the generator stator of Unit #1, the heaviest part of the Pakistan Jamshoro 2×660MW Ultra-supercritical Coal-fired Power Plant Project, was successfully lifted and installed.
The net weight of the generator stator is 450t and the dimensions are 11,635mm (L)×5,096mm (W)×4,531mm (H). The lifting and installation were performed with a 630t crawler crane and a stand-jack system.