Dubai Hassyan Project Unit #1 Successfully Realized Full-load Power Generation

Date:2020-07-01 1872Font scaling:
 

7.1.jpg

Dubai Hassyan Clean Coal-fired Power Plant Project Unit #1 Successfully Realized Full-load Power Generation

At 20:43 on June 30, Dubai local time, Unit #1 of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project successfully realized full-load power generation. As well as being the first clean coal-fired power plant in the Middle East, this project is also a major international cooperation project under the Belt and Road Initiative contracted by HE. It performed with normal parameters, stable equipment operation and excellent operation performance.