News > HE News
HE News
- 19 08 / 2024
First Steel Structure Hoisting for Main Plant Building of Mymensingh Project in Bangladesh Successfully Completed
Recently, Harbin Electric International Co., Ltd. successfully completed the first steel structure hoisting for the main plant building of the Mymensingh 420MW Combined-cycle Project in Bangladesh. Th...… - 17 04 / 2024
First Main Transformer for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan Successfully Shipped
On April 15, the body of the first main transformer for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan, undertaken by Harbin Electric International Co., Ltd., was successfully...… - 06 04 / 2024
First Gas Turbine and Gas Turbine Generator for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan Successfully Shipped
On April 5, the load-out and shipment package including first gas turbine, gas turbine generator, and other core equipment for the Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekist...…
-
-
20 Warm Tips for Epidemic Prevention and Control of Overseas Employees for Harbin Electric Corporation
In order to strengthenpersonal protection of overseas employees, Press Center of HE and HEI have formulated 20 Warm tips for Epidemic Prevention andControl of Overseas Employees for Harbin Electric Corporation with reference torelated information, and put forward suggestions and warm tips for thefollowing epidemic prevention and control of employees for overseas project ofHarbin Electric Corporation for reference.1596 -
Harbin Electric Corporation Signed a Contract for Supply of Three Sets of Main Equipment for Yulin Energy’s Yanghuopan 2×660MW Coal-Electricity Integration Project
On March 30, Harbin Electric Corporation and Shaanxi Yulin Energy Group Co., Ltd. signed a contract in Harbin for the supply of three sets of main equipment for Yulin Energy’s Yanghuopan 2×660MW Coal-electricity Integration Project.1722 -
Boiler Steam Purging Completed for Unit 1 of Hassyan Project in Dubai
At 14:28 on March 23 (Dubai time), the boiler steam purging was completed for Unit 1 of the Hassyan Project. This marks the beginning of the start-up and commissioning stage for the first unit of the project, laying a solid foundation for subsequent grid-connected power generation of unit.1950 -
Harbin Electric Corporation Set a New Record in High-platform Layout of Product at Guohua Jinjie Power Plant
On March 11, at Shaanxi’s Guohua Jinjie Power Plant, Harbin Electric Corporation successfully hoisted the stator of the first fully-air-cooled generator unit into place.1623