Successful First Boiler Hydrostatic Test for the Tarakan Project in Indonesia
On February 27th, local time, the first boiler hydrostatic test for the Tarakan 2×150MW Biomass Coupled Self-Provided Power Plant Project (hereinafter referred to as the "Tarakan Project") in Indonesia was successfully conducted. This marks another significant milestone achieved in the construction of the Tarakan Project following the completion of the first boiler hydrostatic test on December 30, 2023. It provides favorable conditions for the subsequent acid cleaning and ignition blowing of the second boiler.
According to the engineering construction plan, the Tarakan Biomass Coupled Self-Provided Power Plant is scheduled to complete the installation of equipment for the first unit by June this year and enter the preparatory stage for trial operation. The Tarakan Project team will continue to work hard, make concerted efforts, and plan comprehensively to ensure the timely and high-quality completion of each milestone task.