Steam Blowing of HRSG of Unit #2 of the 900MW Combined Cycle BQPS-III Project Successfully Completed

Date:2022-10-07 1144Font scaling:
 

555.png

At 13:07 on October 6in Pakistan, the steam blowing of HRSG #2 of the 900MW Combined Cycle BQPS-III Project, contracted by HE, was completed successfully, laying a solid foundation for the start-up of the entire unit #2.