HRSG Hydrostatic Test of Pakistan Jamshoro 2×660 MW Ultra-supercritical Coal-fired Power Plant Project Successfully Completed

Date:2022-04-28 1265Font scaling:
 

04_编辑.jpg

On April 27th, local time, a successful HRSG hydrostatic test was carried out for HEI’s Pakistan Jamshoro 2×660 MW Ultra-supercritical Coal-fired Power Plant Project.

During the construction of the HRSG, the project department completed a total of 49,338 hydraulic welds, with the monthly number of welds reaching 6,000 and the pass rate reaching 99.7% during the peak period, thereby successfully reaching this milestone.