The first steel structure hoisting of the Unit 1 heat recovery steam generator of Pakistan BQPS III 900MW Combined Cycle Power Plant Project was completed

Date:2020-09-25 1775Font scaling:
 

binjiashneg.jpg

On September 25, local time, the first steel structure hoisting of the Unit 1 heat recovery steam generator of Pakistan BQPS III 900MW Combined Cycle Power Plant Project undertaken by Harbin Electric International Company Limited was completed, marking the project entering into a new stage. At present, the project has completed 90% of the pile foundation construction of the whole plant, and other construction works are proceeding smoothly as planned.