Boiler Steam Purging Completed for Unit 1 of Hassyan Project in Dubai
At 14:28 on March 23 (Dubai time), the boiler steam purging was completed for Unit 1 of the Hassyan Project. This marks the beginning of the start-up and commissioning stage for the first unit of the project, laying a solid foundation for subsequent grid-connected power generation of unit.
The Hassyan Project now is at an important stage of overall construction of four units. While fully organizing the grid-connected power generation for Unit 1, the Hassyan Project team has also completed the casting of 1800m3 of turbine generator foundation slabs for Unit 3, among other tasks.