At 14:00 local time on May 21st in Uzbekistan, the low-pressure cylinder placement for the turbine of the Uzbekistan Sirdarya Phase II 1600MW Combined Cycle Power Plant Project, undertaken by Harbin Electric International Co., Ltd. (HEI), officially began. This marks the formal commencement of the turbine main body installation work.
Recently, Harbin Electric International Co., Ltd. (HEI) received a letter of appreciation from Barqi Tojik (Tajikistan National Power Company), highly commending HEI's professional competence and sense of responsibility demonstrated during the overhaul work at Dushanbe No. 2 Power Plant.
At 8:00 PM local time on April 30th in Pakistan, Unit 1 of the Pakistan Jamshoro 2x660MW Power Plant Project, undertaken by Harbin Electric International Co., Ltd. (HEI), successfully completed its 168-hour reliability run two months ahead of the contract schedule. The unit operated stably with all parameters performing well.The 168-hour reliability run is the final phase of the unit's grid con...
At 15:56 local time on April 16th in Turkey, the main steam pipeline purging for the Turkey Modern Paper PM6 Paperboard Mill Project, undertaken as an EPC (Engineering, Procurement, and Construction) contract by Harbin Electric International Co., Ltd. (HEI), was successfully finalized. This milestone signifies the complete conclusion of purging operations for all five principal steam pipelines,...
On April 14th, a delegation led by Mr. Jasim Thabet, Group CEO of Abu Dhabi National Energy Company (TAQA), comprising senior executives from the Saudi Rumaila Phase II and Nairyah Phase II project owners, conducted an on-site inspection and survey at Harbin Electric International Co., Ltd. (HEI)'s Rumaila Phase II project site. Both parties engaged in in-depth discussions concerning the projec...
On February 13 (local time) in Indonesia, the Tarakan 2x150MW Biomass Coupled Self-provided Power Plant Project, undertaken by HEI, successfully received the trial operation certificate for #2 unit. With this, both units of the project have successfully passed trial operation on the first attempt, marking the beginning of the project’s full handover.
The Tarakan 2x150MW Biomass Coupled Self-provided Power Plant Project in Indonesia, undertaken by HEI, has reached a significant milestone. #2 unit successfully connected to the grid on the first attempt, showing qualified parameters for all systems that operated smoothly and excellently.
On December 31 (local time) in Uzbekistan, #1 GT for the Syrdarya II 1600MW Combined Cycle Gas Power Plant, undertaken by HEI, was successfully positioned. This marks another milestone following the successful positioning of the GT generator on December 26. The dual positioning of the GT and generator unfolds the official start of the GT installation work for the project.
On September 26 (local time), the ST foundation concrete casting of the Enersok Syrdarya II Power Plant Project in Uzbekistan, undertaken by HEI, was successfully completed after 31 hours of continuous pouring operations. This marks another milestone following such completed key milestones on site as the foundation of #1 GT and generator, the upper structure of the gas turbine building, and the...
On August 29, at 13:00 and 16:00 (local time), the Tarakan 2x150MW Biomass Coupled Self-provided Power Plant Project in Indonesia, undertaken by HEI, successfully completed two major milestone achievements: #2 generator rotor coupling and #1 unit pipe blowing. This marks the commencement of the later stage of installation of #2 unit and the final preparation for grid connection and power genera...