Recently, Harbin Electric International Co., Ltd. successfully completed the first steel structure hoisting for the main plant building of the Mymensingh 420MW Combined-cycle Project in Bangladesh. This marks the beginning of a new stage in the site construction.
Recently, after more than 16 hours of continuous pouring 1,070 cubic meters of concrete, Harbin Electric International Co., Ltd. successfully completed the important milestone of foundation bottom concreting for gas turbines at the Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan.
On June 1, at 8:35 AM local time in Pakistan, Harbin Electric International Co., Ltd. (HEI) successfully completed the temperature and pressure rise operation for main boiler of Jamshoro 2×660MW Power Plant Project in Pakistan. This achievement enabled the initial main steam blowout, laying a solid foundation for subsequent unit commissioning and grid connection.Jamshoro 2×660MW Power Plant Pro...
On April 15, the body of the first main transformer for Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan, undertaken by Harbin Electric International Co., Ltd., was successfully loaded and shipped from Taicang Port. This represents another milestone in the Syrdarya II project’s shipment progress, following the successful dispatch of the first gas turbine, gas turbine gen...
On April 5, the load-out and shipment package including first gas turbine, gas turbine generator, and other core equipment for the Syrdarya II 1600MW Combined Cycle Gas Power Plant Project in Uzbekistan, undertaken by Harbin Electric International Co., Ltd., were successfully delivered from Kobe Port, Japan. This registers a significant advancement in the project's equipment shipment.
On March 28, Harbin Electric International Co., Ltd. successfully brought Unit 2 of the Generator Emergency Repair Project at the Cam Pha Power Plant in Vietnam to the grid-connected operation on the first attempt and achieved full-load power generation.Both Phases I and II of the Cam Pha Power Plant Project in Vietnam were undertaken by Harbin Electric International Co., Ltd. And the company w...
On March 26, at 8:58 AM local time in Mexico, Harbin Electric International Co., Ltd. successfully completed the first lifting and positioning of the waste heat boiler module for Manzanillo III 350MW combined-cycle project. This milestone marks significant progress in the project's installation upon the completed installation of three turbine modules to date.In the project, there are 12 modules...
On March 5th at 23:30 local time in Pakistan, the Unit 2 of the BQPS-III 900MW Combined Cycle Power Plant Project, constructed by Harbin Electric Corporation International, successfully passed the fuel performance test.The BQPS-III project adopts Siemens dual-fuel 4000F gas turbines. Both units have entered commercial gas operation, and achieved full-site pre-delivery handover in June 2023.
On February 27th, local time, the first boiler hydrostatic test for the Tarakan 2×150MW Biomass Coupled Self-Provided Power Plant Project (hereinafter referred to as the "Tarakan Project") in Indonesia was successfully conducted. This marks another significant milestone achieved in the construction of the Tarakan Project following the completion of the first boiler hydrostatic test on December ...
On February 21st, local time, Harbin Electric Corporation International successfully signed an EPC contract for the Progresiva 250 MW/1000 MWh energy storage project with Progresiva Energy Investment Company in Turkey. Mr. Cevdet Yılmaz, Vice President of Turkey, and Mr. Liu Shaobin, Chinese Ambassador to Turkey, were invited to attend the signing ceremony.