On May 2nd at 7:50 PM local time, the international company under Harbin Electric Group successfully completed the pouring of the first diaphragm wall for the circulating water pump house in the Manzanillo III 350MW Combined Cycle Project in Mexico. All performance indicators met the contract requirements, demonstrating excellent results. The initiation of civil construction for the circulating...
On April 16th at 5:02 AM local time, the international company successfully completed the pouring of the gas turbine foundation for the Manzanillo III 350MW Combined Cycle Project in Mexico. All performance indicators are excellent, meeting the requirements of the contract.Since the commencement of civil subcontracting in March 2023, the Manzanillo III project team has diligently reviewed the c...
On March 23rd, at 9:01 PM local time, Unit 2 of the Amara Single-Cycle to Combined-Cycle Power Plant Expansion Project in Iraq, constructed by Harbin Electric Group, successfully achieved full-load operation, laying a solid foundation for the subsequent project handover.On March 27th, at 10:17 AM local time, a significant milestone was reached in the Harbin Electric Group's construction project...
Recently, Unit 2 of the 2x125MW Al-Amarah Combined Cycle Power Plant Project in Iraq, constructed by Harbin Electric International Company, achieved its first successful grid connection. Currently, the unit is operating smoothly with all parameters in excellent condition.The Al-Amarah project in Iraq holds significant importance as it represents the first EPC power plant contract secured by an ...
On February 20th at 10:00 local time in Indonesia, HEI began pouring concrete for HRSG #1 pile caps of the Indonesian Dalegan Paper Mill 2×150MW Biomass-coupled Captive Power Plant Project. By 21:40 the same day, the task was completed successfully with 185 m3 of concrete poured. The Dalegan project is another power plant project contracted by HEI following the Paiton project and the Banten pro...
On February 13th at 12:30 local time in Iraq, unit #1 of the Al-Amarah Single-cycle Power Plant to Combined-cycle Power Plant Expansion Project, contracted by HEI, successfully achieved full-load operation. This accomplishment has assisted the project owner in achieving commercial operation and has laid a solid foundation for subsequent project handovers.The Al-Amara project is the first power ...
On January 24, local time in Dubai, HRSG #4 of the Dubai Hassyan Power Plant Project contracted by HEI made its first ignition. This first ignition represents a major milestone in the project and sets the stage for future progress.
At 13:07 on October 6,in Pakistan, the steam blowing of HRSG #2 of the 900MW Combined Cycle BQPS-III Project, contracted by HE, was completed successfully, laying a solid foundation for the start-up of the entire unit #2.
At 12:05 on September 25, in Pakistan, gas turbine #2 of the 900MW Combined Cycle BQPS-III Project, contracted by HEI, was successfully ignited for the first time, with all parameters normal and stable. This marks a key progression point in the construction of unit #2 and takes an important step towards the provisional acquirement of unit #2.
At 11:12 on September 9, in Indonesia, steam turbine unit #2 of the supporting 4×150MW Power Plant of the Lygend Indonesia OBI Nickel-Iron Mine Project, designed and manufactured by HE, was successfully connected to the grid for the first time. It is operating reliably.