On October 9th, at 17:45 local time in Pakistan, Harbin Electric Corporation's International Company achieved the successful 500kV backfeeding of Unit 1 in the Jamshoro 2x660MV Power Station project.The Jamshoro project is situated in the town of Jamshoro, 30 kilometers from Hyderabad in the Sindh province of Pakistan. It boasts a total installed capacity of 1320MW, comprising two 660MW ultra-s...
On October 12th, at 21:05 local time, the performance tests for the No. 4 unit of the Dubai Hassyan Power Station project, constructed by Harbin Electric Corporation's International Company, were completed successfully. All assessment tests under the contract have been successfully conducted, and the unit now meets the requirements for commercial operation. With this achievement, the constructi...
On August 5th, at 15:41 Beijing time, the No. 2 steam turbine unit of Huadian (Indonesia) Borya Power Generation Company, developed by Harbin Electric Corporation, a part of the "Belt and Road" initiative, successfully underwent its initial startup, smoothly reaching a stable speed of 3000 RPM, with outstanding performance across all parameters.The Huadian Indonesia Borya project features a 660...
On July 18th, at local time in Iraq, the Al-Amarah Single-Cycle to Combined-Cycle Power Plant Expansion Project, under the general contracting of Harbin Electric Group's international company, was awarded a temporary handover certificate. Both units had entered the warranty period on June 27th.Since the project's inception, the Al-Amarah project team has overcome multiple difficulties and chall...
On May 15th, at 11:49 AM local time, the international company under Harbin Electric Group achieved the first successful grid connection of Unit 4 in the Dubai Hassyan Power Station Project. The unit's system parameters are operating normally, and the equipment is running smoothly, showcasing excellent operational quality. This achievement marks another significant milestone as the project prog...
On May 2nd at 7:50 PM local time, the international company under Harbin Electric Group successfully completed the pouring of the first diaphragm wall for the circulating water pump house in the Manzanillo III 350MW Combined Cycle Project in Mexico. All performance indicators met the contract requirements, demonstrating excellent results. The initiation of civil construction for the circulating...
On April 16th at 5:02 AM local time, the international company successfully completed the pouring of the gas turbine foundation for the Manzanillo III 350MW Combined Cycle Project in Mexico. All performance indicators are excellent, meeting the requirements of the contract.Since the commencement of civil subcontracting in March 2023, the Manzanillo III project team has diligently reviewed the c...
On March 23rd, at 9:01 PM local time, Unit 2 of the Amara Single-Cycle to Combined-Cycle Power Plant Expansion Project in Iraq, constructed by Harbin Electric Group, successfully achieved full-load operation, laying a solid foundation for the subsequent project handover.On March 27th, at 10:17 AM local time, a significant milestone was reached in the Harbin Electric Group's construction project...
Recently, Unit 2 of the 2x125MW Al-Amarah Combined Cycle Power Plant Project in Iraq, constructed by Harbin Electric International Company, achieved its first successful grid connection. Currently, the unit is operating smoothly with all parameters in excellent condition.The Al-Amarah project in Iraq holds significant importance as it represents the first EPC power plant contract secured by an ...
On February 20th at 10:00 local time in Indonesia, HEI began pouring concrete for HRSG #1 pile caps of the Indonesian Dalegan Paper Mill 2×150MW Biomass-coupled Captive Power Plant Project. By 21:40 the same day, the task was completed successfully with 185 m3 of concrete poured. The Dalegan project is another power plant project contracted by HEI following the Paiton project and the Banten pro...