On April 18th, local time, Unit K3 of the Karachi Nuclear Power Plant in Pakistan, which uses China's third-generation Hualong One nuclear reactor, the fourth unit in the world and second overseas, passed its provisional acceptance, marking the first four Hualong One reactors with the main pumps supplied by Harbin Electric Power Equipment Company Limited: Karachi Units K2 and K3 have now been f...
On March 29th, local time, the steam blowing of HRSG #1 and the hydrostatic test of HRSG #2 of HEI’s Pakistan BQPS-III Project were successfully completed. The completion of these two key milestones on the same day has laid a solid foundation for the subsequent full-load operation of Unit #1, while also marking key progress in the installation of HRSG #2.
At 13:25 on March 26th, local time, the key milestone of boiler steam blowing for Unit #3 of HEI’s Dubai Hassyan Project was successfully completed, laying a solid foundation for the unit’s first connection to the grid.In order to successfully complete the boiler steam blowing work of Unit #3, the project department actively coordinated with the owner and other relevant parties, undertook car...
At 13:30 on March 14th, local time, gas turbine #1 of HEI’s Pakistan 900 MW Combined Cycle BQPS-III Project was successfully ignited for the first time with normal and stable parameters across the board, marking key progress in the installation and commissioning of Unit #1 and the auxiliary systems of the plant, and an important step taken towards the provisional acceptance of the PTOC of Unit...
At 17:38 on February 7th (Iraq local time), the 72-hour reliability operation test of Unit #1 of the Basra Project in Iraq, the equipment of which was supplied by Harbin Turbine Company Limited, was successfully completed with excellent performance indicators, marking a good start to the new year!This power plant project is located in Basra in southern Iraq. It involves the addition of ten HRSG...
At 14:30 on February 17th (Dubai local time), the boiler acid pickling of Unit #3 of the Dubai Hassyan Project contracted by HEI was successfully completed, laying a solid foundation for its subsequent ignition and steam blowing.In order to ensure the successful completion of the acid pickling of Unit #3, the Hassyan Project Department actively carried out meticulous organization and planning, ...
On February 12th (Pakistan local time), the chemical water system of the Jamshoro Project contracted by HEI successfully produced acceptable demineralized water with a conductivity of 0.056 μs/cm, marking the successful completion of the project’s first commissioning milestone and ushering in the new year of 2022 with a good start.With the initiation of commissioning work, the Jamshoro Projec...
At 0:08 a.m. on February 9th (Iraq local time), the steam blowing of HRSG #2 of the Amarah Single Cycle to Combined Cycle Project contracted by HEI was successfully completed.
A few days ago, Heilongjiang Mechanical Engineering Society organized a scientific and technological achievement evaluation meeting in HBC. Upon evaluation by the experts at the meeting, one technology developed by HBC was found to have reached the leading international level and another four scientific and technological achievements have reached the advanced international level.At the meeting,...
On December 30, unit #1 of Fengning Pumped Storage Power Station, with the largest installed capacity in the world, developed by HE, was officially put into operation. The unit operates smoothly with excellent vibration, run-out and temperature rise data and all indicators reach the high-quality standard, which is highly praised by the Owner.