At 19:10 on July 15, local Dubai time, the HRSG hydrostatic test of Unit #4 of the HEI contracted Hassyan Power Plant Project was completed for the first time. The event marked the completion of the installation of the HRSG proper of Unit #4, after which the insulation works will be carried out in full swing.Unit #4 of the Hassyan Power Plant Project is presently at the peak of construction and...
On June 14, local Pakistan time, the acid pickling of HRSG #2 of the HEI contracted 900MW Combined Cycle BQPS-III Project was successfully completed, marking the completion of the installation of HRSG #2 and a solid step towards the ignition of Unit #2.
On May 26, local Pakistan time, steam turbine unit #1 of the HEI contracted 900MW Combined Cycle BQPS-III Project was warmed up successfully with an engaged SSS clutch. Unit #1 was also connected to the grid for combined cycle power generation. The unit is currently working stably with normal parameters. The combined cycle power generation of Unit #1 has been another major milestone since gas t...
At 11:51 on May 16, local time, Unit #3 of the HEI contracted Dubai Hassyan Power Plant Project was connected to the grid successfully for the first time. The parameters were all normal, equipment operation was stable, and operation performance was excellent, marking another major milestone in the project. The Hassyan Power Plant Project has already switched to natural gas to replace coal. Each...
On April 27th, local time, a successful HRSG hydrostatic test was carried out for HEI’s Pakistan Jamshoro 2×660 MW Ultra-supercritical Coal-fired Power Plant Project.During the construction of the HRSG, the project department completed a total of 49,338 hydraulic welds, with the monthly number of welds reaching 6,000 and the pass rate reaching 99.7% during the peak period, thereby successfully...
On April 18th, local time, Unit K3 of the Karachi Nuclear Power Plant in Pakistan, which uses China's third-generation Hualong One nuclear reactor, the fourth unit in the world and second overseas, passed its provisional acceptance, marking the first four Hualong One reactors with the main pumps supplied by Harbin Electric Power Equipment Company Limited: Karachi Units K2 and K3 have now been f...
On March 29th, local time, the steam blowing of HRSG #1 and the hydrostatic test of HRSG #2 of HEI’s Pakistan BQPS-III Project were successfully completed. The completion of these two key milestones on the same day has laid a solid foundation for the subsequent full-load operation of Unit #1, while also marking key progress in the installation of HRSG #2.
At 13:25 on March 26th, local time, the key milestone of boiler steam blowing for Unit #3 of HEI’s Dubai Hassyan Project was successfully completed, laying a solid foundation for the unit’s first connection to the grid.In order to successfully complete the boiler steam blowing work of Unit #3, the project department actively coordinated with the owner and other relevant parties, undertook car...
At 13:30 on March 14th, local time, gas turbine #1 of HEI’s Pakistan 900 MW Combined Cycle BQPS-III Project was successfully ignited for the first time with normal and stable parameters across the board, marking key progress in the installation and commissioning of Unit #1 and the auxiliary systems of the plant, and an important step taken towards the provisional acceptance of the PTOC of Unit...
At 17:38 on February 7th (Iraq local time), the 72-hour reliability operation test of Unit #1 of the Basra Project in Iraq, the equipment of which was supplied by Harbin Turbine Company Limited, was successfully completed with excellent performance indicators, marking a good start to the new year!This power plant project is located in Basra in southern Iraq. It involves the addition of ten HRSG...