Bear the Hope of China’s Industrial Sector, and Showcase China’s Strength in Power Generation
News

Pakistan Jamshoro 2x660MW Ultra-Supercritical Power Plant Project Successfully Completes 168-Hour Reliability Run Test

click:

Date:2025-05-05

At 8:00 PM local time on April 30th in Pakistan, Unit 1 of the Pakistan Jamshoro 2x660MW Power Plant Project, undertaken by Harbin Electric International Co., Ltd. (HEI), successfully completed its 168-hour reliability run two months ahead of the contract schedule. The unit operated stably with all parameters performing well.

The 168-hour reliability run is the final phase of the unit's grid connection and handover assessment, and a crucial milestone in the construction of an EPC power plant project. The Jamshoro project team worked in close cooperation with all construction subcontractors and maintained efficient communication with the owner and supervisory units. They actively coordinated work deployment and ensured 24-hour rotating shifts for on-site personnel to conduct inspections, ensuring that any potential emergencies could be discovered and resolved promptly.







TOP