On February 13th at 12:30 local time in Iraq, unit #1 of the Al-Amarah Single-cycle Power Plant to Combined-cycle Power Plant Expansion Project, contracted by HEI, successfully achieved full-load operation. This accomplishment has assisted the project owner in achieving commercial operation and has laid a solid foundation for subsequent project handovers.The Al-Amara project is the first power ...
On January 24, local time in Dubai, HRSG #4 of the Dubai Hassyan Power Plant Project contracted by HEI made its first ignition. This first ignition represents a major milestone in the project and sets the stage for future progress.
At 13:07 on October 6,in Pakistan, the steam blowing of HRSG #2 of the 900MW Combined Cycle BQPS-III Project, contracted by HE, was completed successfully, laying a solid foundation for the start-up of the entire unit #2.
At 12:05 on September 25, in Pakistan, gas turbine #2 of the 900MW Combined Cycle BQPS-III Project, contracted by HEI, was successfully ignited for the first time, with all parameters normal and stable. This marks a key progression point in the construction of unit #2 and takes an important step towards the provisional acquirement of unit #2.
At 11:12 on September 9, in Indonesia, steam turbine unit #2 of the supporting 4×150MW Power Plant of the Lygend Indonesia OBI Nickel-Iron Mine Project, designed and manufactured by HE, was successfully connected to the grid for the first time. It is operating reliably.
On August 27, in Iraq, unit #2 of the Salah al-Din 2×630MW Oil-and Gas-fired Power Plant Project, developed and manufactured by HE, was successfully connected to the grid for the first time. Currently, the unit’s operation is stable with excellent parameters, laying a solid foundation for its subsequent commercial operation.
Recently, the Dubai Hassyan Project, contracted by HEI, has achieved the important milestone of safe operation for 7 million continuous hours.Mohammad Abunayyan, executive manager of the Project, issued the Safety Management Certificate to HEI’s Hassyan Project Department.
Recently, Engineering News-Record (ENR),the most authoritative academic magazine in the global construction industry, announced its 2022 Top 250 International Contractors. HEI is included for the 9th year in a row, ranking 85th on the full list and 21st among the 79 Chinese companies on the list. The ENR is a trustworthy ranking recognized in the global construction industry. It comprehensivel...
July 30, 2022 at 10:14 local Dubai time, the 10KV switchgear of the Unit #4 of the HEI contracted Dubai Hassyan Power Plant Project was successfully energized, marking the successful completion of the backfeeding of Unit #4, the subsequent commissioning of which will be gradually carried out in an all-round way.The successful completion of the milestone of backfeeding provides a strong guarante...
Units #4 and #5 of Zetes III in Turkey, which were overhauled by HEI, were recently successfully connected to the grid with a load of up to 600MW. The units are working stably with all indicators (especially the vibration data of the steam turbine) significantly better than before the overhaul, marking the success of the Zetes III overhaul.The successful completion of the overhaul has been high...