On the afternoon of November 18, 2021, Harbin Electric Corporation convened a personnel meeting with middle and above levels management. Officials from the Organization Department of the CPC Central Committee announced the CPC Central Committee’s decision on the adjustment of the chairman and the secretary of the party committee of Harbin Electric Corporation: Cao Zhi’an was appointed as the ...
On November 13, the backfeeding of the 900MW Combined Cycle BQPS-III contracted by HEI and the energization of the 132kV Landhi substation were successfully completed, making it the first energized substation of BQPS-III.
On October 22 at 15:00, HEI and EREN Group signed the Modern Karton PM6 Project EPC Contract through a video conference.The PM6 project will use the most advanced paper machines, producing 2,400 tons of recycled corrugated cardboard per day, with an annual output of 700,000 tons and a wastewater treatment capacity of 20,160m3/day.EREN Group, as a strong integrated enterprise in Turkey, plays a ...
On October 18, the China Wind Power 2021 was grandly opened at the China International Exhibition Center in Beijing, and Harbin Electric Wind Power was invited to attend the exhibition.Harbin Electric Wind Energy, as a leading enterprise in the R&D and manufacturing of wind power equipment in China and one of the important wind power equipment manufacturing bases, has been committed to promotin...
On October 4, unit #14 of the Baihetan Hydropower Project, the world’s first mega-kilowatt unit developed by HE, passed its 100th day of stable operation, with various data and indicators better than those of the Baihetan high-quality units.The first 100-day stable operation means that generator units newly put into operation ran stably for 100 consecutive days and successfully passed the insp...
Recently, HE successfully passed a number of key milestones in the core assembly system of WTGS HE187-6750 with fully independent intellectual property rights. Among them, the general assembly function commissioning and the comprehensive performance test of the main transmission chain and the main power chain in the workshop and the on-site assembly of the first innovative steel tube concrete l...
On September 20, local time in Pakistan, HRSG #1 of the BQPS-III Combined-cycle Power Plant Project contracted by HE completed the hydrostatic test successfully at the first time, marking the installation of HRSGs has made a key progress and laying a foundation for the acid pickling and the steam blowing.According to the EPC contract, the HRSGs of this project have to obtain the ASME certificat...
On September 4, local time in Dubai, Unit #2 of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project, a major international cooperation project contracted by HE under the Belt and Road Initiative and the first clean coal-fired power plant in the Middle East, completed the performance test successfully, marking that all the assessment tests under the contract were successfully complete...
At 18:00 on August 25, local time in Dubai, Unit #2 of Dubai Hassyan 4x600MW Clean Coal-fired Power Plant Project contracted by HE passed the operation reliability test successfully, with normal parameters, stable operation and excellent operation performance.
Recently, Engineering News-Record (ENR), the world's most authoritative academic magazine in the field of engineering construction, released the list of "ENR's 2021 Top 250 International Contractors". HEI was shortlisted for the 8th time among the Top 100, rising from last year's 95th to 78th this year, and ranked 19th among the 78 Chinese companies on the list.The ENR ranking is an authoritati...