Concrete Poured Successfully for the HRSG Pile Caps of the Indonesian Dalegan Paper Mill Biomass-coupled Captive Power Plant Project

click:

Date:2023-02-23

 

On February 20th at 10:00 local time in Indonesia, HEI began pouring concrete for HRSG #1 pile caps of the Indonesian Dalegan Paper Mill 2×150MW Biomass-coupled Captive Power Plant Project. By 21:40 the same day, the task was completed successfully with 185 m3 of concrete poured. 

图片44.jpg

The Dalegan project is another power plant project contracted by HEI following the Paiton project and the Banten project in Indonesia. The project execution team is 