On August 16 local time in Bangladesh, the main installation of the gas turbine generator unit for the Mymensingh 420 MW Combined-Cycle Power Plant Project, constructed by Harbin Electric International Company Limited (HEI), was successfully completed.
At 14:16 local time on August 15 in Turkey, the Modern Karton PM6 Paperboard Mill Project, constructed by Harbin Electric International Company Limited (HEI), was successfully started up. The paper machine’s pulp feeding and all operating indicators demonstrated excellent performance.The project execution team of HEI carried out meticulous planning and careful coordination, efficiently integra...
On July 24 local time in Uzbekistan, the rotor installation for the steam turbine generator of the 1600 MW Syrdarya II Combined-Cycle Gas Turbine Power Plant Project, constructed by Harbin Electric International Company Limited (HEI), was successfully completed.
On July 9, the Tarakan 2x150MW Biomass Coupled Self-provided Power Plant Project in Indonesia (referred to as the "Tarakan Project"), undertaken by Harbin Electric International Company (HEI), officially awarded the Temporary Taking-Over Certificate (TOC). Both generating units have successfully entered the warranty period, and the overall project schedule meets the requirements of the main con...
At 3:53 a.m. local time on June 22 in Mexico, the main transformer of the 350 MW gas turbine unit at the Manzanillo III Combined-Cycle Project, constructed by Harbin Electric International Company Limited (HEI), successfully completed its first energization and remained stable. All transformer indicators performed well, laying a solid foundation for the comprehensive commissioning of the projec...
At 14:00 local time on May 21st in Uzbekistan, the low-pressure cylinder placement for the turbine of the Uzbekistan Sirdarya Phase II 1600MW Combined Cycle Power Plant Project, undertaken by Harbin Electric International Co., Ltd. (HEI), officially began. This marks the formal commencement of the turbine main body installation work.
Recently, Harbin Electric International Co., Ltd. (HEI) received a letter of appreciation from Barqi Tojik (Tajikistan National Power Company), highly commending HEI's professional competence and sense of responsibility demonstrated during the overhaul work at Dushanbe No. 2 Power Plant.
At 8:00 PM local time on April 30th in Pakistan, Unit 1 of the Pakistan Jamshoro 2x660MW Power Plant Project, undertaken by Harbin Electric International Co., Ltd. (HEI), successfully completed its 168-hour reliability run two months ahead of the contract schedule. The unit operated stably with all parameters performing well.The 168-hour reliability run is the final phase of the unit's grid con...
At 15:56 local time on April 16th in Turkey, the main steam pipeline purging for the Turkey Modern Paper PM6 Paperboard Mill Project, undertaken as an EPC (Engineering, Procurement, and Construction) contract by Harbin Electric International Co., Ltd. (HEI), was successfully finalized. This milestone signifies the complete conclusion of purging operations for all five principal steam pipelines,...
On April 14th, a delegation led by Mr. Jasim Thabet, Group CEO of Abu Dhabi National Energy Company (TAQA), comprising senior executives from the Saudi Rumaila Phase II and Nairyah Phase II project owners, conducted an on-site inspection and survey at Harbin Electric International Co., Ltd. (HEI)'s Rumaila Phase II project site. Both parties engaged in in-depth discussions concerning the projec...