At 16:38 on July 15, Pakistan local time, the HRSG #1 foundation pile cap of the 900MW Bin Qasim Combined-cycle Power Station III (BQPS-III) contracted by HEI saw its first cubic meter of concrete poured. The whole pouring job was completed at 9:58 in the morning on July 16, taking a total of 17 hours and 20 minutes with 530 cubic meters of concrete poured.The Project, with two sets of 4000F si...
At 17:35 on July 3, Dubai local time, the Unit #2 boiler hydrostatic test of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project contracted by HEI was completed successfully, which marked the substantial completion of the installation of Unit #2’s main boiler components, creating favorable conditions for subsequent boiler thermal insulation and laying a solid foundation for Unit #2 ...
Dubai Hassyan Clean Coal-fired Power Plant Project Unit #1 Successfully Realized Full-load Power GenerationAt 20:43 on June 30, Dubai local time, Unit #1 of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project successfully realized full-load power generation. As well as being the first clean coal-fired power plant in the Middle East, this project is also a major international cooperat...
At 2:30 a.m. on June 13, installation officially began on the world’s first turbine, manufactured by HE, situated on the right bank of the Baihetan Dam. The bottom ring of the unit was also successfully lifted into the equipment pit. After successful fabrication of the bottom ring, it was divided into four parts which were delivered to the construction site separately. At the site, through the...
On June 2, Ecuador local time, HE, along with CELEC SUR, the Employer of the Minas-San Francisco Hydroelectric Project, HIDROJUBONES, the Supervisor, and the Project’s civil works handover and acceptance committee officially signed the final handover minutes for the civil works of the Minas-San Francisco 3×90MW Hydroelectric Project in Ecuador. The handover marked the successful completion of ...
At 13:45 on May 18th, 2020, local time in Dubai, Unit 1 of Dubai Hassyan 4×600MW clean coal power plant project contracted by China Harbin Electric Corporation successfully achieved synchronization at one attempt. The parameters of various systems of the unit were normal, and the equipment was running smoothly with excellent quality.As a major power project of “the Belt and Road” internationa...
At 10:58 am on April 24, Pakistan local time, excavation work began for the foundation of a waste heat boiler, part of the BIN QASIM Phase III 900MW Combined Cycle Power Station Project in Pakistan. This marks the beginning of a new stage of construction for the BIN QASIM Phase III Project.
A few days ago, the first four-nozzle coal-water-slurry gasifier for the Inner Mongolia Huineng Coal Chemical Phase II Project, developed by HE, was successfully produced and shipped.With a daily coal feeding quantity of 3,300 tons, this gasifier has the largest daily coal feeding quantity in the world, and breaks the previous record of another coal-water-slurry gasifier with a 3,000-ton daily ...