click:
Date:2021-02-19
Recently, the 50MW circulating fluidized bed boiler self-developed by Harbin Electric Corporation Boiler Company as a “One Belt, One Road” project for Unit 1 of Indonesia’s North Sumatra 3 Power Plant successfully passed 96+72 hours of test operation and was put into commercial operation. During test operation, the unit operated stably and all parameters met design standards, earning the customer’s complete approval.