News > HE News
HE News
- 06 03 / 2024
Successful Fuel Performance Test for Unit 2 of the BQPS-III 900MW Combined Cycle Power Plant Project in Pakistan
On March 5th at 23:30 local time in Pakistan, the Unit 2 of the BQPS-III 900MW Combined Cycle Power Plant Project, constructed by Harbin Electric Corporation International, successfully passed the fue...… - 29 02 / 2024
Successful First Boiler Hydrostatic Test for the Tarakan Project in Indonesia
On February 27th, local time, the first boiler hydrostatic test for the Tarakan 2×150MW Biomass Coupled Self-Provided Power Plant Project (hereinafter referred to as the "Tarakan Project") in Indonesi...… - 23 02 / 2024
Harbin Electric Corporation International Secures Energy Storage Project EPC Contract
On February 21st, local time, Harbin Electric Corporation International successfully signed an EPC contract for the Progresiva 250 MW/1000 MWh energy storage project with Progresiva Energy Investment ...…
-
HEI and EREN Group Sign the Modern Karton PM6 Project EPC Contract
On October 22 at 15:00, HEI and EREN Group signed the Modern Karton PM6 Project EPC Contract through a video conference.1476 -
Harbin Electric Wind Power Attends China Wind Power 2021
On October 18, the China Wind Power 2021 was grandly opened at the China International Exhibition Center in Beijing, and Harbin Electric Wind Power was invited to attend the exhibition.1541 -
The World's First Mega-kilowatt Unit Developed by HE Has Operated Stably for the First 100 Days
On October 4, unit #14 of the Baihetan Hydropower Project, the world’s first mega-kilowatt unit developed by HE, passed its 100th day of stable operation, with various data and indicators better than those of the Baihetan high-quality units.1054 -
-
HRSG #1 of BQPS-III Project Completes the Hydrostatic Test Successfully at the First Time
On September 20, local time in Pakistan, HRSG #1 of the BQPS-III Combined-cycle Power Plant Project contracted by HE completed the hydrostatic test successfully at the first time, marking the installation of HRSGs has made a key progress and laying a foundation for the acid pickling and the steam blowing.828