- 06 03 / 2024
Successful Fuel Performance Test for Unit 2 of the BQPS-III 900MW Combined Cycle Power Plant Project in Pakistan
On March 5th at 23:30 local time in Pakistan, the Unit 2 of the BQPS-III 900MW Combined Cycle Power Plant Project, constructed by Harbin Electric Corporation International, successfully passed the fue...… - 29 02 / 2024
Successful First Boiler Hydrostatic Test for the Tarakan Project in Indonesia
On February 27th, local time, the first boiler hydrostatic test for the Tarakan 2×150MW Biomass Coupled Self-Provided Power Plant Project (hereinafter referred to as the "Tarakan Project") in Indonesi...… - 23 02 / 2024
Harbin Electric Corporation International Secures Energy Storage Project EPC Contract
On February 21st, local time, Harbin Electric Corporation International successfully signed an EPC contract for the Progresiva 250 MW/1000 MWh energy storage project with Progresiva Energy Investment ...…
-
Unit #2 of Dubai Hassyan Clean Coal-fired Power Plant Project Starts Commercial Operation
On September 4, local time in Dubai, Unit #2 of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project, a major international cooperation project contracted by HE under the Belt and Road Initiative and the first clean coal-fired power plant in the Middle East, completed the performance test successfully, marking that all the assessment tests under the contract were successfully completed and Unit #2 is ready for commercial operation.841 -
Unit #2 of Dubai Hassyan Clean Coal-fired Power Plant Project Passes the Operation Reliability Test Successfully
At 18:00 on August 25, local time in Dubai, Unit #2 of Dubai Hassyan 4x600MW Clean Coal-fired Power Plant Project contracted by HE passed the operation reliability test successfully, with normal parameters, stable operation and excellent operation performance.788 -
HEI Ranks 78th on the List of
Recently, Engineering News-Record (ENR), the world's most authoritative academic magazine in the field of engineering construction, released the list of "ENR's 2021 Top 250 International Contractors".784 -
HE Signs a Cooperation Agreement with Vietnam PECC2
At 11 o'clock on the morning of August 17, HEI and Vietnam PECC2 signed a cooperation agreement through a video conference.1769 -
The Groundbreaking Ceremony Is Held for the Pakistan Tarbela 5 Hydropower Extension Project
On August 12, local time, the Pakistani Tarbela 5 Hydropower Extension Project, in which HEI is involved, held a groundbreaking ceremony in Tarbela of KPK Province, marking the start of the extension of the Tarbela 5 Hydropower, the largest and most important hydropower plant in Pakistan.1685