News > HE News
HE News
- 04 01 / 2021
Hoisting of Boiler #4 Steel Structures for the Dubai Hassyan Project Started
On January 1, 2021, at 9:19 a.m. Dubai local time, the first steel structure of boiler #4 for the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project contracted by HEI was successfully hoisted ...… - 04 01 / 2021
Main Structure of the Central Control Building of the BQPS-III Project Successfully Completed
At 6:45 on January 3, local time, the roof of the central control building of the 900MW Combined Cycle BQPS-III Project contracted by HEI was successfully poured, with a total of 397m3 of concrete pou...… - 23 12 / 2020
Provisional Acceptance Certificate Issued for Turkey's Soma Project
On December 21, local time, KOLIN, owner of the Turkey Soma 2×255MW Coal-fired Power Plant Project, officially issued the provisional acceptance certificate (PAC) to HEI, marking the end of the constr...…
-
The Belt and Road | GIS Room Roofs of Offsite KTPS and Landhi Substations of BQPS-III Successfully Poured
On November the 2nd and 3rd, the GIS room roofs of the offsite KTPS and Landhi substations of the 900MW Combined-cycle BQPS-III contracted by HEI were poured respectively, with a total of 193 m3 concrete, which marks the completion of the construction of the main structure of the GIS room, laying a solid foundation for subsequent masonry works.501 -
One Belt One Road | Hardworking Gift for National Day The Foundation Concrete Pouring of the Unit 4 Heat Recovery Steam Generator of Amara project in Iraq is Successfully Completed
At 9 o'clock on October 6th, local time, the concrete pouring work for the foundation of the Unit 4 heat recovery steam generator of Iraq Amara project undertaken by HEI was successfully completed, which took 13 hours.699 -
One Belt One Road | National Day Gifts First Concrete Pouring of Unit 4 Foundation of Dubai Hassyan Clean Coal-fired Power Plant Project is Successfully Completed
At 19:00 on October 2nd, local time, the first concrete pouring of Unit 4 foundation of Dubai Hassyan 4×600MW clean coal-fired power station project undertaken by HEI was successfully completed.457 -
The first steel structure hoisting of the Unit 1 heat recovery steam generator of Pakistan BQPS III 900MW Combined Cycle Power Plant Project was completed
On Sep.25,the first steel structure hoisting of the Unit 1 heat recover steam generator of #HE’s Pakistan BQPS III 900MW Combined Cycle Power Plant Project was completed.468 -
World-class "Super Project": The biggest of the world 1000MW hydro-generator rotor of the Baihetan right bank Power Station developed by Harbin Electric Corporation was successfully hoisted
World-class "Super Project": The biggest of the world 1000MW hydro-generator rotor of the Baihetan right bank Power Station developed by Harbin Electric Corporation was successfully hoisted.627