- 06 03 / 2024
Successful Fuel Performance Test for Unit 2 of the BQPS-III 900MW Combined Cycle Power Plant Project in Pakistan
On March 5th at 23:30 local time in Pakistan, the Unit 2 of the BQPS-III 900MW Combined Cycle Power Plant Project, constructed by Harbin Electric Corporation International, successfully passed the fue...… - 29 02 / 2024
Successful First Boiler Hydrostatic Test for the Tarakan Project in Indonesia
On February 27th, local time, the first boiler hydrostatic test for the Tarakan 2×150MW Biomass Coupled Self-Provided Power Plant Project (hereinafter referred to as the "Tarakan Project") in Indonesi...… - 23 02 / 2024
Harbin Electric Corporation International Secures Energy Storage Project EPC Contract
On February 21st, local time, Harbin Electric Corporation International successfully signed an EPC contract for the Progresiva 250 MW/1000 MWh energy storage project with Progresiva Energy Investment ...…
-
First Cubic Meter of Concrete Successfully Poured for the Foundation Pile Cap of the BQPS-III HRSG in Pakistan
At 16:38 on July 15, Pakistan local time, the HRSG #1 foundation pile cap of the 900MW Bin Qasim Combined-cycle Power Station III (BQPS-III) contracted by HEI saw its first cubic meter of concrete poured.1253 -
First-Time Successful Completion of the Dubai Hassyan Project Unit #2’s Boiler Hydrostatic Test
At 17:35 on July 3, Dubai local time, the Unit #2 boiler hydrostatic test of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project contracted by HEI was completed successfully, which marked the substantial completion of the installation of Unit #2’s main boiler components, creating favorable conditions for subsequent boiler thermal insulation and laying a solid foundation for Unit #2 boiler acid pickling and ignition venting.1185 -
-
Dubai Hassyan Project Unit #1 Successfully Realized Full-load Power Generation
At 20:43 on June 30, Dubai local time, Unit #1 of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project successfully realized full-load power generation.1594 -
Installation Officially Starts on the World’s First Turbine on the Right Bank of the Baihetan Dam, Manufactured by HE
At 2:30 a.m. on June 13, installation officially began on the world’s first turbine, manufactured by HE, situated on the right bank of the Baihetan Dam. The bottom ring of the unit was also successfully lifted into the equipment pit.1451